Heliconias Project

The transportation of 7 transformers from San Jerónimo Antioquia to Heliconias was executed.

Main difficulties: The access road to the project is an extremely narrow and complex tertiary route for the use of heavy equipment due to its condition and deterioration. Millions of dollars were invested for adaptation, pruning of trees (rapid growth given the area), retaining walls, water management on the road and paving of certain curves with complicated cambers and uneven ground. Very narrow villages were crossed where the management of communities and the adequacy of walls, roofs, sidewalks and poles were indispensable. 12 people were involved in the logistics of transporting each of the transformers.

Dimensions: Length: 7.4meters Width:4.3meters Height:4.3meters.

Weight: 128 tons

Used equipment: 10 lines of Goldhofer self-propelled modular, Sany 750 ton crane, Liebherr 500 ton crane.

Recent Posts

Barbados

Project carried out in mid 2020, one month of continuous operation for which personnel (7 people)

Barrancabermeja Reactor

A reactor was transported and installed for the ecopetrol plant in Barrancabermeja. Transportes Montejo moved the

Mining Sholves

Several mining shovels have been transported throughout this year 2020 and previous years. This machinery is

Steam Boiler Dome

This dome was transported from Cartagena to Cali for the client Incauca. Main difficulties: Road “la

Boeing 707

In 2018 a challenging service was obtained by the Colombian Air Force to mobilize one of

Heliconias Project

The transportation of 7 transformers from San Jerónimo Antioquia to Heliconias was executed. Main difficulties: The